Judge blocks Trump's 250-foot arch hours after his planning panel approved it
Judge Tanya Chutkan found Congress never authorized the arch and halted all construction at Memorial Circle for 14 days.
A federal judge late Thursday blocked President Trump from breaking ground on his 250-foot arch at the edge of Arlington National Cemetery, less than two hours after a federal planning commission led by a Trump appointee approved it.
U.S. District Judge Tanya Chutkan granted a temporary restraining order sought by the District of Columbia and Virginia. It bars any construction-related work at Memorial Circle for 14 days, NPR reported. The administration had told the court it could start excavating that same day.
Memorial Circle is the traffic island at the Virginia end of Arlington Memorial Bridge. The National Capital Planning Commission approved the arch 8-4 after nearly nine hours of public testimony, mostly from opponents, CBS News reported.
Congress never signed off
In a 33-page opinion in the consolidated cases Lemmon v. Trump and District of Columbia v. National Park Service, Chutkan found D.C. and Virginia are likely to win. Federal law requires Congress to specifically authorize any monument on Park Service land in the capital. Congress passed no such law. "Defendants complied with none of these procedures," she wrote.
The Justice Department argued a 1925 bridge law already covered the arch. That law approved two 166-foot columns that were never built. The arch would be 50% taller and block the view of the Lincoln Memorial from the Lee Mansion, the judge wrote: "merely to state this argument is to reveal its flaws."
A security case that showed up late
The administration also claimed, through declarations from Defense Secretary Pete Hegseth and Homeland Security Secretary Markwayne Mullin, that the arch would bring "significant national security benefits." Chutkan found those claims unsupported. They appear nowhere in the planning documents and surfaced for the first time in a brief filed last week, she wrote.
Who pays
Construction would cut westbound traffic off the bridge to two lanes and close the circle to northbound drivers, according to the government's own environmental review, cited in the opinion. Officials have said crews would work 20 hours a day, year-round, for two to three years, NPR reported. The cost, and who pays it, remains unknown.
What's next
The order runs 14 days. Chutkan put off ruling on a longer stay and on an injunction request from three Vietnam veterans and an architectural historian who sued in February. Rep. Don Beyer (D-Va.) has a bill to ban and defund the arch, with 80 co-sponsors, and Democrats take the House majority in January.